Job won Shire of Wandering — Main Street resurfacing | RF-2026-0912 | Ch 0–850, full width 7.2 m | 3 crews across 3 days
Sales handoff
Quote 12 — two pages

Stage 1 — Spray seal

Tuesday 15 September 2026, 07:00 to 15:00, Spray Seal Crew 2. Two-coat seal over prepared pavement, Ch 0 to Ch 850, full width 7.2 m including shoulders. 10/7 two-coat seal, C170 bitumen with 0.5% adhesion agent, to MRWA Specification 503 Bituminous Surfacing. Sealed area 6,120 m².

Stage 2 — Asphalt (follows Stage 1)

Wednesday 16 September 2026, 07:00 to 16:00, Asphalt Crew 1. 30 mm dense-graded overlay at the two intersections, Ch 300 and Ch 520, including tie-ins. DG10 asphalt, 30 mm compacted, C320 binder, to MRWA Specification 504. Overlay 640 m².

Stage 3 — Line marking (follows Stage 2)

Thursday 17 September 2026, 08:00 to 13:00, Line Marking Crew 1. Reinstate centre line, edge lines and intersection holding lines, Ch 0 to Ch 850. Waterborne paint with glass beads, 100 mm lines. Longitudinal 2,550 m.

Site access

School zone Ch 300 to Ch 520: no plant movements 08:00 to 09:00 or 15:00 to 15:45. Traffic management to Shire-approved TMP 26-114. Site contact Peta Lang, Shire Works Supervisor.
Mobilisation pack for your approval
Three job cards · three calendar slots
TUE 15 SEP Ready
Spray seal
Spray Seal Crew 2
Treatment
Spec
6,120 m² 07:00–15:00
WED 16 SEP Ready
Asphalt
Asphalt Crew 1
Treatment
Spec
640 m² after Stage 1
THU 17 SEP Drafting
Line marking
Line Marking Crew 1
Treatment
Start 08:00 sits inside the school-zone window. Supervisor to confirm.
2,550 m
Nothing reaches a crew until you approve it.