Site Photos
Framing 85%
Framing — Front elevation
Framing 85%
Framing — Rear wall
Electrical 15%
Electrical — Rough-in bedroom 1
Electrical 15%
Electrical — Switchboard
Roof 100%
Roof — Tiles laid
Roof 100%
Roof — Completed
Plumbing 40%
Plumbing — Bathroom stack
Plaster 60%
Plaster — Living room
Plaster 60%
Plaster — Kitchen
Generated Progress Report
Weekly Progress Report
47 Smith St, Craigieburn — Week ending 14 March 2026
Executive Summary
Trade Progress
| Trade | Last Week | This Week | Change | Status |
|---|---|---|---|---|
| Framing | 70% | 85% | +15% | On track |
| Electrical | 0% | 15% | +15% | Commenced |
| Plumbing | 40% | 40% | 0% | Stalled |
| Roof | 90% | 100% | +10% | Complete |
| Plaster | 30% | 60% | +30% | On track |
| Tiling | 0% | 0% | 0% | Not started |
Risk Flags
⚠️
Plumbing stalled — no progress since last week. Recommend follow-up with plumber.
⚠️
Tiling not commenced — was scheduled to start this week. Delay may impact handover.
2 rain days this week (Tue, Thu) — affected external works